| Project
Timeline |
Key
Events in 2010 |
- March 20 - Employee Sneak Peek
- March 23 - Community Preview
- April 8 - Mock Patient Move
- May 25 and June 8 - Day in the Life exercises
- June 6 - Public Open House
- June 22 - New Hospital opens
- October 18 - LEED Gold Certified
|
Key
Events in 2009
|
- April - Arbor Day celebration
- June - Groundbreaking for Hahn Cancer Center
- July - Bovis Lend Lease marks 2.25 million safe hours on site
- July - New RMH corporate identity introduced
- December - Substantial construction completion
|
Key
Events in 2008 |
- April - "Topping out" beam is placed
- December
- Bovis Lend Lease celebrates 1 million safe hours on site
|
Key
Events in 2007 |
- February
- RMH unveils interior and exterior renderings of the new
hospital.
- Late Feb./early March - Site
grading completed (for Phase I)
- March - Deep
foundation work
- July - Shallow
foundation/deep foundation work - begins at the end of deep
foundation work
- Late fall/early winter - Structural
steel begins
|
Key
Events in 2006 |
- June
- RMH holds groundbreaking for new hospital with more than
500 in attendance.
- September - Site grading begins.
- December
- State Certificate of Public Need for new hospital is signed
by state Commisioner of Health.
|
Key
Events in 2005 |
- August
- RMH receives recommendation for rezoning of property from
County Planning Commission.
- October
- RMH receives approval for rezoning of property from County
Board of Supervisors.
- December
- Harman land purchase is finalized.
- December
- JMU purchase of RMH property completed (RMH has leaseback
agreement).
|
Key Events in 2004 |
- September
- RMH announces plans to build a new hospital and health
campus to serve the community for the next 100 years.
- December
- RMH announces purchase of Harman farm as the site for
the new hospital and health campus.
- December - JMU announces intent to purchase current
15-acre hospital campus adjacent to JMU.
|